The groundworks package on a new life-sciences facility has handed over on programme, ready for superstructure to commence.
AAC has completed the groundworks package on a new life-sciences facility, with handover to the superstructure team taking place on programme this month. The package covered bulk excavation, attenuation, foundations, drainage and the slab.
Life-science facilities run on tight floor-level tolerances and on a programme that has to hand over to a clean-room follow-on without rework. Our team set out the slab levels to a single-millimetre tolerance and built the pour windows around the M&E first-fix requirements.
You only get one shot at a life-science slab. We don't move on until it's surveyed, signed and accepted.Site Engineering team
Follow-on works begin shortly: superstructure, MEP first-fix and external infrastructure. AAC continues to provide site logistics and HSEQ support across the wider programme.